NEW MAPLEWOOD SCHOOL
Schedule Update
This week our build team is focusing on:
1. Steel and structural columns are quickly being erected. The team is assembling what will become the 7/8 house area.
2. Concrete decks floors have been poured in the 7/8 house.
3. Forming the road that will ultimately surround the new school and the property. This will also assist moving construction vehicles around the property.
4. Excavating and pouring concrete footers and foundation is almost complete.
5. Underground main sewer has been installed within building footprint.
6. West side block masonry and fire walls of the Band, Choir, Music and Tech Ed wing are going up quickly.
7. Geo Thermal Well Drillers are drilling the 160 wells over the next 2-3 months. Currently over 20 wells bored and set.
Other coordination items:
1. Ongoing pilot of new furniture styles by staff.
2. Preparing working lists of building internal needs (paper towel, soap dispensers..etc)
3. Continue final interior design material selections.
|